hospital design Juli Johnson

Delivering Care at Speed: An MEPFP Story of Collaboration, Innovation, and Purpose

By Juli Johnson, Principal, Healthcare studio

The Northside Hospital Gwinnett patient tower expansion is the largest healthcare project in our firm’s history. Juli Johnson, Principal in our Healthcare studio, shares how early engagement, early procurement, and one aligned team delivered it at speed and within budget.

Key Takeaways

  • Engaging the full team during concept design gave the owner analyzed, priced options before key decisions became fixed.
  • In inpatient healthcare, MEPFP systems shape decisions that can read as architectural, including floor-to-floor heights, central plant location, and site infrastructure.
  • Early procurement and pull planning for long-lead equipment kept the project moving as scope and scale changed.
  • Planning for flexibility at four levels, from a central plant that can back-feed the hospital to future vertical expansion, supports the owner’s long-term goals

When a community needs more hospital beds, every decision carries urgency. Delivering a high-rise patient tower at unprecedented speed took accelerated schedules and technical expertise. It also took an owner-led culture of trust, an integrated team willing to rethink conventional practices, and a shared commitment to reaching the finish line together.

For our engineering team, the project was a defining example of what is possible when planning, design, procurement, and construction move as one coordinated effort with a common purpose: bringing needed care capacity to the community as quickly as possible and within budget.

The expansion added 15 floors and 240 beds and doubled the hospital’s capacity.

Northside Hospital Gwinnett patient tower expansion

Northside Hospital Gwinnett

Engaged Early, Aligned From the Start

One of the project’s most important advantages was the owner’s decision to engage the full project team during concept design. Architects, engineers, constructors, clinical stakeholders, and the owner’s representatives were all at the table early, before key decisions became fixed.

That early engagement created space to understand the project at a campus level: its goals, budget, criteria, operational needs, constraints, infrastructure opportunities, and long-term vision. It also let the team evaluate multiple concepts, multiple times, using a target value delivery approach before committing to a single solution with unknown cost and impacts.

In complex inpatient healthcare, MEPFP systems shape the feasibility of planning decisions from the very beginning. The building floor-to-floor heights, the location of the central plant (inboard vs. outboard), the distribution of mechanical and electrical spaces throughout the program, the underground site infrastructure, and other key decisions that can be perceived as architectural decisions were analyzed with input from our team. Engaging our team this early allowed every option to be brought forward, carefully analyzed, weighed, and priced, so the owner’s final decisions fully accounted for mechanical and electrical systems.

The result was faster decision-making and better decision-making. The owner had the information needed to select a path forward with confidence, understanding both the immediate implications and the long-term operational value of each concept.

Responding to a Changing Need

The speed-to-market mandate was driven by two converging realities: sustained growth in the community and the urgent capacity demands created by the COVID-19 pandemic. The need for beds was immediate.

During design development, the planned height of the high-rise patient tower nearly doubled. Later, the project’s scope and scale adjusted again. Each change was necessary for the hospital to achieve the goals of its leadership, and each raised a consequential engineering question: How could the infrastructure accommodate the change and hold the schedule?

Our approach was rooted in nimble, solution-oriented problem solving. The team continuously reevaluated options, identified impacts, and developed practical paths forward to keep progress moving. That required deep technical knowledge and an understanding that engineering decisions had to support the project’s larger objective: delivering capacity when the community needed it most.

We needed to be flexible, and we had to work together as a cohesive team. And by team, I mean the general contractor, the architect, ourselves, the engineers, and the owner.

Juli Johnson Interview

Rethinking Procurement and Planning

When this project began, early procurement was an occasional, sometimes uncomfortable proposition. It has since become standard industry practice.

This project changed everyone’s mindset. The team reached across the table to plan the early and carefully timed procurement of numerous systems, including generators, switchgear, chillers, cooling towers, and air handling units. With systems like generators carrying lead times of over one year, the team needed to pull plans carefully, engage vendors and trade partners, and align on equipment details very early.

Design, construction, and owner stakeholders worked together to identify critical systems and equipment, assess risks, and make informed decisions earlier than would typically occur. Those conversations required trust. Team members had to raise suggestions, question assumptions, and openly discuss potential outcomes on both sides.

The owner established the conditions that made this possible. Its leadership model encouraged the group to operate as one team, with every organization invested in the shared result. Existing relationships among team members provided a strong foundation, while new relationships developed through a shared commitment to transparency, accountability, and the project’s ultimate purpose.

Pull-planning exercises were another essential part of the process. The team identified mechanical and electrical needs, mapped the sequence of events required to support coordination, and confirmed milestones across design, procurement, construction, and commissioning activities. This approach made dependencies visible early, so the team could coordinate decisions around equipment releases, room layouts, structural requirements, installation sequencing, and system startup.

Thought Leadership That Created Options

A project like this calls for deep expertise: a team well versed in mechanical and electrical healthcare best practice, made up of healthcare engineers who work day in and day out solving problems and designing solutions for inpatient healthcare settings. Our team was able to come to the table listening to the criteria and goals, and turn that information into engineering solutions that were innovative, future oriented, flexible, and practical.

Planning for flexibility was another area where our team provided leadership, and it came through on several levels. First, in the infrastructure, we planned a new central plant that could serve the expansion and also back-feed the entire hospital, all while maintaining N+1 redundancy. Second, flexibility was built in for changes in the hospital program over the life of the building. Third, flexibility was included for future vertical expansion. The final flexibility was more in mindset. It meant recognizing that the most effective solution was sometimes the less familiar one: the one that best advanced the owner’s goals, the project’s real-world constraints, and the engineering needs.

The campus infrastructure side of the Northside story is told in Hospital Campus Master Planning by Adam Bare

Juli Johnson and Adam Bare at Northside Hospital Gwinnett

Juli Johnson and Adam Bare at Northside Hospital Gwinnett

One Team, One Outcome

The defining characteristic of this project was the team’s collective focus on the end goal and how we would get there together.

The team demonstrated that speed to market is achieved through early alignment, listening, informed decision-making, technical leadership, communication, and a willingness to solve problems together as a team.

Most importantly, it demonstrates the value of a shared purpose. Every design and construction decision served one commitment: delivering beds, and care, to a community that needed them.

Today we have three patient tower expansions with Northside at various stages of design and construction.

Juli Johnson Walkthrough

Must See

Explore how Newcomb & Boyd partners with health systems and architects to design facilities where patient care comes first.